Operation
Atacama Kozan
Atacama Kozan produced 10.2 kt of fine copper in the 12 months to July 2026. That is 11.83% less than in the 12 months before (11.6 kt). It is the 29th largest of the 33 operations the table details and accounts for 0.2% of the country's copper.
Fine copper, 12 months to July 2026
10.2 kt
11.83%against the 12 months before
January to July 2026
5.3 kt
20.8%against the same period of 2025
Share of the country's copper
0.2%
29th of 33 operations
Who is behind it
Holder before the SMA (the environmental regulator)
SCM Atacama Kozan SMA
It holds 5 environmental permits of the 5 of this operation's regulated unit.
Owners of SCM Atacama Kozan
We do not yet have a publishable source on its owners.
Output month by month
Thousand tonnes of fine copper at 100% of the operation, since January 2014.
The last twelve months
| Month | Output | A year earlier | Change | Source |
|---|---|---|---|---|
| July 2026 | 0.6 | 1.1 | 49.61% | Cochilco |
| June 2026 | 0.6 | 0.8 | 14.91% | Cochilco |
| May 2026 | 1.1 | 0.9 | 16.14% | Cochilco |
| April 2026 | 0.8 | 0.9 | 12.57% | Cochilco |
| March 2026 | 0.6 | 1.1 | 49.36% | Cochilco |
| February 2026 | 0.8 | 0.8 | 6.13% | Cochilco |
| January 2026 | 0.8 | 1 | 16% | Cochilco |
| December 2025 | 1.1 | 1 | 11.26% | Cochilco |
| November 2025 | 0.9 | 1.1 | 18.75% | Cochilco |
| October 2025 | 1 | 1.2 | 17.42% | Cochilco |
| September 2025 | 1.1 | 0.9 | 13.35% | Cochilco |
| August 2025 | 0.9 | 0.7 | 29.26% | Cochilco |
Output by year
Thousand tonnes of fine copper. Up to 2025, yearly figures; after that, the sum of its months.
See the figures by year
| Year | Output | Source |
|---|---|---|
| 2026 | 5.3 kt | 7 months |
| 2025 | 11.6 kt | Cochilco |
| 2024 | 11.5 kt | Cochilco |
| 2023 | 13.7 kt | Cochilco |
| 2022 | 13.8 kt | Cochilco |
| 2021 | 12.2 kt | Cochilco |
| 2020 | 13.2 kt | Cochilco |
| 2019 | 12.5 kt | Cochilco |
| 2018 | 12.2 kt | Cochilco |
| 2017 | 10.1 kt | Cochilco |
| 2016 | 13.1 kt | Cochilco |
| 2015 | 14.1 kt | Cochilco |
| 2014 | 13.7 kt | Cochilco |
| 2013 | 12.6 kt | Cochilco |
| 2012 | 12.7 kt | Cochilco |
| 2011 | 13.1 kt | Cochilco |
| 2010 | 8.6 kt | Cochilco |
| 2009 | 8.8 kt | Cochilco |
| 2008 | 13.8 kt | Cochilco |
| 2007 | 18.4 kt | Cochilco |
| 2006 | 16.1 kt | Cochilco |
| 2005 | 21.4 kt | Cochilco |
| 2004 | 23.8 kt | Cochilco |
Environmental enforcement
7 records of the SMA on this operation's regulated unit.
- 6 Inspections
- 1 Sanction procedure
Each record, with its case number, its status and its fine, is on the platform.
The output figures are those of Cochilco's monthly table and yearbook, at 100% of the operation. The 12-month totals, the year-to-date figures and the changes are our own sums and differences on those figures. The sentences of this page are assembled from them: no language model is involved.