Skip to content
Projects with environmental approval

Other · DIA

Prospección Minera Cachiyuyo

Sociedad Contractual Minera Rock Exploration — Freirina · Atacama

Declared investment

US$ 300 k

Dollars of the evaluation year SMA

Approval

Feb 21, 2012

RCA 35/2012 · Aprobado

Site

Rock Exploration- Prospección Minera Cachiyuyo

1 environmental approval at this site

File

Instrument
Environmental impact declaration (DIA)
Project type
Prospecciones y exploraciones
Company
Sociedad Contractual Minera Rock Exploration
Comunas
Freirina · Atacama
Assessed in
Región de Atacama

Timeline

  1. Aug 29, 2011Submitted for environmental assessment
  2. Feb 21, 2012Environmental approval (DIA)176 days later

Source: public registers of Chile's environmental regulator (SMA). Investment is the one the holder declared in the environmental assessment, in dollars of that year.