Metallic mining · EIA
EIA Ampliación y Mejoras Operacionales en Mina Los Colorados
Cía. Mra. del Pacífico S.A. — Vallenar, Huasco, Freirina · Atacama
Approval
Nov 3, 2010
RCA 246/2010 · Aprobado
Site
CMP-Los Colorados
6 environmental approvals at this site
File
- Instrument
- Environmental impact study (EIA)
- Project type
- Minera metálica
- Company
- Cía. Mra. del Pacífico S.A.
- Comunas
- Vallenar, Huasco, Freirina · Atacama
- Assessed in
- Región de Atacama
- Coordinates
- -28.2895, -70.8084
Timeline
- Nov 3, 2010Environmental approval (EIA)
Enforcement at the site
- Inspections3 · latest in 2019
- Provisional measures3 · latest in 2024
- Compliance programmes1 · latest in 2018
- Sanction proceedings1 · latest in 2018
These cover the whole site, not this project alone.
Other approvals at CMP-Los Colorados
5 more approvals at the same supervised unit.
| Project | Approval | Declared investment | Source |
|---|---|---|---|
| Modificación Plan Minero Mina Los Colorados | 2021RCA 68/2021 | — | SMA |
| Optimización en Almacenamiento y Suministro de Combustible en Mina Los Colorados. | 2017RCA 75/2017 | — | SMA |
| Ampliación Subestación Eléctrica Los Colorados | 2012RCA 21/2012 | — | SMA |
| Recuperación de Mineral de Hierro Contenido en Rechazos de la Planta de Beneficio Los Colorados | Jan 17, 2011DIA · RCA 3/2011 | US$ 7.6 M | SMA |
| Los Colorados Este | May 23, 1997EIA · RCA 4/1997 | US$ 93 M | SMA |
Source: public registers of Chile's environmental regulator (SMA). Investment is the one the holder declared in the environmental assessment, in dollars of that year.