Skip to content
Projects with environmental approval

Metallic mining · DIA

Nuevas Pilas de Lixiviación

Compañía Minera Dayton Sociedad Contractual Minera — Andacollo · Coquimbo

Declared investment

US$ 1 M

Dollars of the evaluation year SMA

Approval

Jan 8, 2014

RCA 131/2013 · Aprobado

Site

Dayton

6 environmental approvals at this site

File

Instrument
Environmental impact declaration (DIA)
Project type
Minera metálica
Company
Compañía Minera Dayton Sociedad Contractual Minera
Comunas
Andacollo · Coquimbo
Assessed in
Región de Coquimbo

Timeline

  1. Jan 8, 2014Environmental approval (DIA)

Enforcement at the site

  • Inspections27 · latest in 2023
  • Compliance programmes1 · latest in 2014
  • Sanction proceedings1 · latest in 2014

These cover the whole site, not this project alone.

Other approvals at Dayton

5 more approvals at the same supervised unit.

ProjectApprovalDeclared investmentSource
Modificación RCA N°16 Continuidad Operacional 2015 - 2020Dec 11, 2014DIA · RCA 151/2014US$ 5 MSMA
Proyecto Andacollo Oro - Medidas para el Cumplimiento del Plan de Descontaminación de AndacolloFeb 18, 2013DIA · RCA 16/2013US$ 32 MSMA
Modificación Plan Minero 2007-2010Nov 27, 2008EIA · RCA 360/2008US$ 3.5 MSMA
Plan Minero 2007-2010Apr 21, 2007DIA · RCA 74/2007US$ 700 kSMA
Proyecto Desarrollo Fase IV - Andacollo OroJan 3, 2006DIA · RCA 155/2005—SMA

Source: public registers of Chile's environmental regulator (SMA). Investment is the one the holder declared in the environmental assessment, in dollars of that year.