Explotación Subterránea Mina Faride (Reingreso)

Explotadora Minera del Cerro S.A. — Sierra Gorda · Antofagasta

Declared investment

US$ 3 M

Dollars of the evaluation year SMA

Approval

Jan 7, 2010

RCA 436/2009 · Aprobado

Site

Explotación Subterránea Mina Faride

1 environmental approval at this site

File

Instrument
Environmental impact declaration (DIA)
Project type
Prospecciones y exploraciones
Company
Explotadora Minera del Cerro S.A.
Comunas
Sierra Gorda · Antofagasta
Assessed in
Región de Antofagasta

Timeline

  1. Aug 21, 2009Submitted for environmental assessment
  2. Jan 7, 2010Environmental approval (DIA)139 days later

Source: public registers of Chile's environmental regulator (SMA). Investment is the one the holder declared in the environmental assessment, in dollars of that year.