Skip to content
Projects with environmental approval

Metallic mining · DIA

Algorta - Fase II

Algorta Norte S.A. — Sierra Gorda, Mejillones, Antofagasta · Antofagasta

Declared investment

US$ 30 M

Dollars of the evaluation year SMA

Approval

Dec 6, 2013

RCA 360/2013 · Aprobado

Site

Algorta

5 environmental approvals at this site

File

Instrument
Environmental impact declaration (DIA)
Project type
Minera metálica
Company
Algorta Norte S.A.
Comunas
Sierra Gorda, Mejillones, Antofagasta · Antofagasta
Assessed in
Región de Antofagasta

Timeline

  1. Dec 6, 2013Environmental approval (DIA)

Enforcement at the site

  • Inspections2 · latest in 2023
  • Sanction proceedings1 · latest in 2025

These cover the whole site, not this project alone.

Other approvals at Algorta

4 more approvals at the same supervised unit.

ProjectApprovalDeclared investmentSource
DIA-Planta de Nitratos y Productos Derivados de Sales.May 27, 2015DIA · RCA 210/2015US$ 120 MSMA
Modificación Proyecto Minero Algorta Sector PampaJul 29, 2010DIA · RCA 224/2010US$ 6.4 MSMA
Modificación Proyecto Minero Algorta Sistema de Bombeo de Agua de Mar y del Tendido EléctricoJan 27, 2010DIA · RCA 8/2010US$ 4 MSMA
Proyecto Minero AlgortaMay 25, 2009EIA · RCA 174/2009US$ 110 MSMA

Source: public registers of Chile's environmental regulator (SMA). Investment is the one the holder declared in the environmental assessment, in dollars of that year.