Skip to content
Projects with environmental approval

Metallic mining · DIA

Proyecto Botadero Farellones II

Minera Las Cenizas S.A. — Cabildo · Valparaíso

Declared investment

US$ 45 k

Dollars of the evaluation year SMA

Approval

Jan 4, 2005

RCA 274/2004 · Aprobado

Site

Planta Cabildo Minera Las Cenizas

7 environmental approvals at this site

File

Instrument
Environmental impact declaration (DIA)
Project type
Minera metálica
Company
Minera Las Cenizas S.A.
Comunas
Cabildo · Valparaíso
Assessed in
Región de Valparaíso

Timeline

  1. Jan 4, 2005Environmental approval (DIA)

Enforcement at the site

  • Inspections5 · latest in 2025
  • Sanction proceedings1 · latest in 2025
  • Provisional measures1 · latest in 2024

These cover the whole site, not this project alone.

Other approvals at Planta Cabildo Minera Las Cenizas

6 more approvals at the same supervised unit.

ProjectApprovalDeclared investmentSource
Continuidad Operacional Mina Sauce2024RCA 202405001171/2024—SMA
Disposición de Relave en Pasta en Interior MinaNov 9, 2023RCA 202305001187/2023—SMA
Mejoramiento Instalaciones Planta de Procesamiento de Minerales CabildoFeb 11, 2013DIA · RCA 29/2013US$ 3 MSMA
Depósito de Pasta - CabildoNov 22, 2007EIA · RCA 337/2007US$ 6 MSMA
Proyecto Depositación de Relaves Espesados Interior Mina CabildoAug 8, 2005DIA · RCA 199/2005US$ 4 MSMA
Proyecto Botadero Las Guias IIDec 30, 2004DIA · RCA 268/2004US$ 46 kSMA

Source: public registers of Chile's environmental regulator (SMA). Investment is the one the holder declared in the environmental assessment, in dollars of that year.