Línea de Transmisión Eléctrica 110 KV Proyecto Refugio

Cía. Minera Maricunga — Atacama

Declared investment

—

Not stated in the register SMA

Approval

2004

RCA 5/2004 · Aprobado

Site

Kinross -Refugio

8 environmental approvals at this site

File

Instrument
—
Project type
Metallic mining
Company
Cía. Minera Maricunga
Comunas
Atacama
Assessed in
Atacama

Timeline

The register gives only the year of the approval: 2004.

Enforcement at the site

  • Inspections4 · latest in 2017
  • Sanction proceedings2 · latest in 2015
  • Final sanctions2 · latest in 2015
  • Provisional measures1 · latest in 2016

These cover the whole site, not this project alone.

Other approvals at Kinross -Refugio

7 more approvals at the same supervised unit.

ProjectApprovalDeclared investmentSource
Modificación Proyecto Minero Refugio Racionalización de la Operación Mina PlantaMar 3, 2011DIA · RCA 45/2011US$ 285 MSMA
Optimización Proceso Productivo Proyecto RefugioNov 10, 2009DIA · RCA 268/2009US$ 37.5 MSMA
Modificación Instalaciones y Diseños Proyecto RefugioJan 16, 2004DIA · RCA 4/2004US$ 114 MSMA
Nuevo Campamento Proyecto RefugioDec 30, 2003DIA · RCA 97/2003US$ 5.2 MSMA
Plan de Cierre Proyecto RefugioJun 11, 2002DIA · RCA 56/2002US$ 180 kSMA
Modificación Proyecto RefugioMay 16, 2000DIA · RCA 32/2000US$ 1.9 MSMA
Proyecto Minero RefugioDec 14, 1994EIA · RCA 2/1994US$ 127 MSMA

Source: public register of environmental approvals. This register states neither the investment nor the day of the resolution; the location is the site's.