Skip to content
Projects with environmental approval

Metallic mining

Adecuación Operacional Faena Minera Caserones

Minera Lumina Copper Chile Ltda. — Atacama

Declared investment

—

Not stated in the register SMA

Approval

Jul 21, 2025

RCA 202503001105/2025 · Aprobado

Site

Caserones

8 environmental approvals at this site

File

Instrument
—
Project type
Metallic mining
Company
Minera Lumina Copper Chile Ltda.
Comunas
Atacama
Assessed in
Atacama

Timeline

  1. Jun 8, 2020Submitted for environmental assessment
  2. Jul 21, 2025Environmental approval (RCA)1,869 days later

Enforcement at the site

  • Inspections11 · latest in 2022
  • Sanction proceedings3 · latest in 2021
  • Final sanctions2 · latest in 2019
  • Provisional measures2 · latest in 2018
  • Compliance programmes1 · latest in 2021

These cover the whole site, not this project alone.

Other approvals at Caserones

7 more approvals at the same supervised unit.

Source: public register of environmental approvals. This register states neither the investment nor the day of the resolution; the location is the site's.