Skip to content
Projects with environmental approval

Metallic mining

Cierre Operacional Mina Cardenilla

Soc. Exploración y Desarrollo Minero (Explodesa) — Valparaíso

Declared investment

—

Not stated in the register SMA

Approval

Nov 25, 2025

RCA 202505001211 · Aprobado

Site

Mina Cardenilla

2 environmental approvals at this site

File

Instrument
—
Project type
Metallic mining
Company
Soc. Exploración y Desarrollo Minero (Explodesa)
Comunas
Valparaíso
Assessed in
Valparaíso

Timeline

  1. Jan 12, 2021Submitted for environmental assessment
  2. Nov 25, 2025Environmental approval (RCA)1,778 days later

Enforcement at the site

  • Compliance programmes2 · latest in 2019
  • Sanction proceedings2 · latest in 2019
  • Inspections1 · latest in 2017
  • Final sanctions1 · latest in 2018

These cover the whole site, not this project alone.

Other approvals at Mina Cardenilla

1 more approval at the same supervised unit.

ProjectApprovalDeclared investmentSource
Proyecto Mina CardenillaMar 27, 2008DIA · RCA 242/2008—SMA

Source: public register of environmental approvals. This register states neither the investment nor the day of the resolution; the location is the site's.