Metallic mining
Modificación Minera Amax Guanaco
Antofagasta
Approval
—
RCA · MODIFICACION MINERA AMAX GUANACO · Aprobado
Site
Mina Guanaco
14 environmental approvals at this site
File
- Instrument
- —
- Project type
- Metallic mining
- Company
- —
- Comunas
- Antofagasta
- Assessed in
- Antofagasta
- Coordinates
- -25.1074, -69.5383
- Tracked project: Modificación Minera Amax Guanaco
Timeline
- Jun 24, 1997Submitted for environmental assessment
Enforcement at the site
- Inspections1 · latest in 2020
These cover the whole site, not this project alone.
Other approvals at Mina Guanaco
13 more approvals at the same supervised unit.
| Project | Approval | Declared investment | Source |
|---|---|---|---|
| Relixiviación de Ripios Pila 4 Modificación Mina Guanaco | 2022RCA 20220200163/2022 | — | SMA |
| Modificación Mina Guanaco - Línea Eléctrica 33 KV | 2016RCA 64/2016 | — | SMA |
| Explotación Mina Amancaya | Aug 20, 2015DIA · RCA 319/2015 | US$ 38 M | SMA |
| Proyecto Explotación Nuevo Rajo Quillota en Mina Guanaco | Sep 14, 2012DIA · RCA 209/2012 | US$ 350 k | SMA |
| Transporte y Almacenamiento de Cianuro de Sodio Mina Guanaco | 2010RCA 256/2010 | — | SMA |
| Proyecto Reapertura Mina Guanaco | Jul 23, 2009DIA · RCA 251/2009 | US$ 25 M | SMA |
| Proyecto de Prospección Amancaya | Feb 11, 2009DIA · RCA 38/2009 | US$ 3 M | SMA |
| Prospección Nueva Guanaco Tercera Etapa | Mar 20, 2008DIA · RCA 98/2008 | US$ 3 M | SMA |
| Prospección Nueva Guanaco Segunda Etapa | Mar 30, 2007DIA · RCA 87/2007 | US$ 2.1 M | SMA |
| Prospección Nueva Guanaco | May 4, 2006DIA · RCA 87/2006 | US$ 2 M | SMA |
| Modificación Minera Amax Guanaco | Oct 17, 1997DIA | US$ 6 M | SMA |
| Guanaco | Jul 22, 1993EIA | US$ 70 M | SMA |
| Guanaco | — | — | SMA |
Source: public register of environmental approvals. This register states neither the investment nor the day of the resolution; the location is the site's.