Metallurgy
Transporte de Cristales Solubles Desde La División Codelco Norte Hasta La Planta Santa Margarita
Antofagasta
Approval
2005
RCA 34/2005 · Aprobado
Site
Santa Margarita
3 environmental approvals at this site
File
- Instrument
- —
- Project type
- Metallurgy
- Company
- —
- Comunas
- Antofagasta
- Assessed in
- Antofagasta
- Coordinates
- -22.4670, -68.6905
Timeline
The register gives only the year of the approval: 2005.
Enforcement at the site
- Inspections1 · latest in 2021
These cover the whole site, not this project alone.
Other approvals at Santa Margarita
2 more approvals at the same supervised unit.
| Project | Approval | Declared investment | Source |
|---|---|---|---|
| Ampliación Planta Santa Margarita | Mar 14, 2008DIA · RCA 82/2008 | US$ 16.5 M | SMA |
| Santa Margarita | Jan 26, 2004DIA · RCA 8/2004 | US$ 12 M | SMA |
Source: public register of environmental approvals. This register states neither the investment nor the day of the resolution; the location is the site's.