Mining project in the SEIA · DIA
Modificación Tubería de Agua Proyecto Franke
Sociedad Contractual Minera Franke — Diego de Almagro, Taltal · Interregional
Declared investment
US$ 10 M
Declared by the holder on submission
Submitted to the SEIA
Jul 31, 2007
Decision: Dec 13, 2007
File
- File number
- 2286272
- Instrument
- Environmental Impact Statement (DIA)
- Typology (art. 3 RSEIA)
- i.4) Proyecto de desarrollo minero sobre 5000 tons/mens
- Holder
- Sociedad Contractual Minera Franke
- Region
- Interregional
- Communes
- Diego de Almagro, Taltal
- See the file at SEA
- Company in Veta IQ: Sociedad Contractual Minera Franke
- Environmental approval (RCA): RCA 3156/2007 · Dec 13, 2007
- Tracked project: Modificación Tubería de Agua Proyecto Franke
Other mining projects of the same holder
Mining SEIA files with the same holder, newest first.
- Abastecimiento Agua de Mar Minera FrankeDIA · Approved · Aug 1, 2023 · US$ 28 M
- Abastecimiento Agua de Mar Minera FrankeDIA · Withdrawn · Apr 6, 2023 · US$ 28 M
- Proyecto Actualización Continuidad Franke N° 2DIA · Approved · Nov 4, 2021
- Actualización Continuidad Operacional FrankeDIA · Approved · Apr 9, 2020 · US$ 15 M
- Proyecto Continuidad Operacional FrankeEIA · Approved · Dec 9, 2016 · US$ 15.5 M
- Alternativas de Transporte de Cátodos de Cobre, Proyecto FrankeDIA · Approved · Mar 28, 2013 · US$ 308 M
- Explotación ChinaDIA · Approved · Sep 29, 2008 · US$ 10 M
- Actualización Proyecto FrankeDIA · Approved · Nov 21, 2007 · US$ 160 M
- Proyecto FrankeEIA · Approved · Oct 30, 2006 · US$ 100 M
Source: Servicio de Evaluación Ambiental (SEA), public register of projects submitted to the SEIA. Veta IQ shows the register's facts; the documents of the file are on SEA's website.