Skip to content
Projects with environmental approval

Metallic mining · EIA

Proyecto Tugal

Cía. Mra. San Gerónimo — La Serena · Coquimbo

Declared investment

US$ 7 M

Dollars of the evaluation year SMA

Approval

Feb 13, 2009

RCA 32/2009 · Aprobado

Site

Minera Rendic

12 environmental approvals at this site

File

Instrument
Environmental impact study (EIA)
Project type
Minera metálica
Company
Cía. Mra. San Gerónimo
Comunas
La Serena · Coquimbo
Assessed in
Región de Coquimbo

Timeline

  1. Feb 13, 2009Environmental approval (EIA)

Enforcement at the site

  • Inspections4 · latest in 2023
  • Compliance programmes1 · latest in 2016
  • Sanction proceedings1 · latest in 2016

These cover the whole site, not this project alone.

Other approvals at Minera Rendic

11 more approvals at the same supervised unit.

Source: public registers of Chile's environmental regulator (SMA). Investment is the one the holder declared in the environmental assessment, in dollars of that year.