Skip to content
Projects with environmental approval

Non-metallic mining

Tente en el Aire

SQM — Tarapacá

Declared investment

—

Not stated in the register SMA

Approval

Nov 5, 2021

RCA 20210100112/2021 · Aprobado

Site

Faena Nueva Victoria - SQM

14 environmental approvals at this site

File

Instrument
—
Project type
Non-metallic mining
Company
SQM
Comunas
Tarapacá
Assessed in
Tarapacá

Timeline

  1. Jan 4, 2019Submitted for environmental assessment
  2. Nov 5, 2021Environmental approval (RCA)1,036 days later

Enforcement at the site

  • Inspections8 · latest in 2024

These cover the whole site, not this project alone.

Other approvals at Faena Nueva Victoria - SQM

13 more approvals at the same supervised unit.

ProjectApprovalDeclared investmentSource
Ampliación Zona de Mina Nueva Victoria SurJun 15, 2012DIA · RCA 76/2012US$ 8.5 MSMA
Pampa HermosaSep 1, 2010EIA · RCA 890/2010US$ 1,033 MSMA
Ducto y Pozas de Evaporación IrisMay 19, 2009DIA · RCA 61/2009US$ 45.6 MSMA
Actualización Operación Nueva VictoriaJan 5, 2009DIA · RCA 124/2008US$ 28.4 MSMA
Incorporación de Cloro en Planta de Yodo Nueva Victoria2008RCA 70/2008—SMA
Zona de Mina Nueva VictoriaJun 5, 2008EIA · RCA 42/2008US$ 14.4 MSMA
Modificación Planta de Yoduro Nueva VictoriaJul 28, 2007DIA · RCA 94/2007US$ 8 MSMA
Mina Nueva Victoria SurJan 19, 2007DIA · RCA 173/2006US$ 2.8 MSMA
Proyecto Aducción Llamara2005RCA 32/2005—SMA
Ampliación Nueva VictoriaJan 6, 2005DIA · RCA 4/2005US$ 29 MSMA
Transporte Terrestre de Peroxido de Hidrogeno Entre Iquique y Nueva Victoria (Planta SQM)2002RCA 163/2002—SMA
Extracción de Aguas Subterraneas Desde Salar Sur ViejoDec 23, 1997DIA · RCA 36/1997US$ 2.3 MSMA
Proyecto Lagunas Soquimich-Lodo S.A.Jan 31, 1997EIA · RCA 58/1997US$ 16.9 MSMA

Source: public register of environmental approvals. This register states neither the investment nor the day of the resolution; the location is the site's.