Skip to content
Projects with environmental approval

Metallic mining

Extensión de Vida Util Complejo Productivo Sur (Ex Planta Delta) ENAMI

ENAMI — Coquimbo

Declared investment

—

Not stated in the register SMA

Approval

Aug 19, 2025

RCA 20250400197/2025 · Aprobado

Site

Delta ENAMI

4 environmental approvals at this site

File

Instrument
—
Project type
Metallic mining
Company
ENAMI
Comunas
Coquimbo
Assessed in
Coquimbo

Timeline

  1. Oct 10, 2024Submitted for environmental assessment
  2. Aug 19, 2025Environmental approval (RCA)313 days later

Enforcement at the site

  • Inspections4 · latest in 2015
  • Compliance programmes1 · latest in 2017
  • Sanction proceedings1 · latest in 2017

These cover the whole site, not this project alone.

Other approvals at Delta ENAMI

3 more approvals at the same supervised unit.

ProjectApprovalDeclared investmentSource
Optimización y Regularización de Procesos- Planta DeltaJun 13, 2013DIA · RCA 61/2013US$ 100 kSMA
Ampliación de Proceso Molienda Flotación DeltaDec 2, 2010DIA · RCA 21/2010US$ 1 MSMA
Proyecto DeltaJan 25, 2008EIA · RCA 32/2008US$ 40 MSMA

Source: public register of environmental approvals. This register states neither the investment nor the day of the resolution; the location is the site's.