Projects with environmental approval

Metallic mining

Línea de Transmisión Eléctrica Encuentro - Spence

Minera Spence S.A. — Antofagasta

Declared investment

—

Not stated in the register SMA

Approval

2004

RCA 208/2004 · Aprobado

Site

Spence

12 environmental approvals at this site

File

Instrument
—
Project type
Metallic mining
Company
Minera Spence S.A.
Comunas
Antofagasta
Assessed in
Antofagasta

Timeline

The register gives only the year of the approval: 2004.

Enforcement at the site

  • Inspections8 · latest in 2026

These cover the whole site, not this project alone.

Other approvals at Spence

11 more approvals at the same supervised unit.

ProjectApprovalDeclared investmentSource
Adecuación Operacional SpenceJan 9, 2025RCA 2025020013/2025—SMA
Bahias de Combustible Spence2022RCA 202202001239/2022—SMA
Actualización de los Requerimientos de Materiales Asociados a la Construcción Diferida del Depósito de Relaves2020RCA 64/2020—SMA
Actualización de Manejo de Ripios de Lixiviación - Spence2020RCA 53/2020—SMA
Minerales Primarios Minera Spence2017EIA · RCA 275/2017US$ 2,500 MSMA
Optimización SpenceJun 15, 2011DIA · RCA 112/2011US$ 200 MSMA
Modificaciones Menores en Minera SpenceMay 10, 2010DIA · RCA 140/2010US$ 35 MSMA
Grupos de Generación Eléctrica2008RCA 69/2008—SMA
Actualización Proyecto SpenceFeb 5, 2004DIA · RCA 15/2004US$ 800 MSMA
SpenceDec 27, 2002EIA · RCA 308/2002US$ 800 MSMA
Exploración SpenceJun 8, 1998DIA · RCA 39/1998US$ 4 MSMA

Source: public register of environmental approvals. This register states neither the investment nor the day of the resolution; the location is the site's.