Projects
Projects with environmental approval
1,452 mining projects with an environmental approval (RCA), out of 2,298 approvals at supervised sites of the sector. Each with its date, instrument, declared investment, company and location.
Projects in this selection
1,452
RCAs from 1992 to 2026
Declared investment
US$ 94,035 M
Sum of the 824 projects that state it, in nominal dollars of each evaluation year
Regions
16
Antofagasta 532 · Atacama 352 · Coquimbo 138
Approvals per year
Number of RCAs in the selection by the year they were issued.
1,452 projects
| Project | Company | Location | Approval | Declared investment | Source |
|---|---|---|---|---|---|
| Tranque (Depósito) de Relaves Mantos de Talcuna N°4 Planta Don ArturoMetallurgy · Minera Talcuna | Compañía Minera Cobrex | CoquimboVicuña | Aug 8, 2002DIA | — | SMA |
| Optrimización Planta de Molienda y HarneoNon-metallic mining · Terminal Patillos Sal Lobos - Iquique | Compañía Minera Punta de Lobos S.A. | TarapacáIquique | Aug 6, 2002DIA · RCA 115/2002 | US$ 590 k | SMA |
| Ampliación de la Explotación de Arenas Siliceas en Sector LoancoNon-metallic mining · Proyecto de titular persona natural | — | MauleConstitución | Jul 23, 2002DIA · RCA 158/2002 | US$ 420 k | SMA |
| Modificación de Proyecto Dump LeachMetallic mining · Faena Minera Quebrada Blanca | Teck Quebrada Blanca | TarapacáPica | Jul 22, 2002DIA · RCA 110/2002 | US$ 140 k | SMA |
| Ampliación Planta SX-EW en Planta SaladoMetallurgy · Planta Salado ENAMI | ENAMI | AtacamaChañaral | Jul 12, 2002DIA · RCA 66/2002 | US$ 2.3 M | SMA |
| Prestripping Damiana CentralMetallic mining · Codelco Salvador - Potrerillos | Codelco | AtacamaDiego de Almagro | Jul 12, 2002DIA · RCA 65/2002 | — | SMA |
| Modificación Damiana NorteMetallic mining · Codelco Salvador - Potrerillos | Codelco | AtacamaDiego de Almagro | Jul 4, 2002DIA · RCA 59/2002 | US$ 3 M | SMA |
| Transporte de Concentrado de Cobre al Sector La Negra y ChuquicamataTailings and waste · Transporte Mineroconcentrado de Cobre al Sector La Negra y Chuquicamata Candelaria | Minera Candelaria | AtacamaTierra Amarilla, Taltal, Sierra Gorda, Copiapó, Chañaral, Calama, Antofagasta | Jul 3, 2002DIA · RCA 99/2002 | — | SMA |
| Proyecto Mejoramiento de Eficiencia Stretch PlanMetallic mining · Faena Minera Cerro Colorado | Compañía Minera Cerro Colorado Limitada | TarapacáPozo Almonte | Jul 2, 2002DIA · RCA 102/2002 | US$ 40 k | SMA |
| Planta de Chancado para CalizaNon-metallic mining · Planta de Chancado para Caliza | Agroindustrial Ibarra S.A. | CoquimboLos Vilos | Jun 26, 2002DIA | US$ 410 k | SMA |
| Plan de Cierre Proyecto RefugioMetallic mining · Kinross -Refugio | Cía. Minera Maricunga | AtacamaTierra Amarilla | Jun 11, 2002DIA · RCA 56/2002 | US$ 180 k | SMA |
| Optimización de la Operación Actual a 114 KTPD (Minera Los Pelambres)Metallic mining · Minera Los Pelambres | Minera Los Pelambres | CoquimboSalamanca, Los Vilos, Illapel | Jun 3, 2002DIA · RCA 108/2002 | US$ 24 M | SMA |
| Explotación Arenas Silicicas-Pertenencias Loanco 9-1 al 5Non-metallic mining · Minera Faro Carranza/Pirazzoli | Minera Faro Carranza S.A. | MauleChanco | May 31, 2002DIA · RCA 102/2002 | US$ 200 k | SMA |
| Lloimavida Explotación de Minerales de Zeolita a Rajo AbiertoNon-metallic mining · Lloimavida Explotación de Zeolita a Rajo Abierto | — | MauleParral | May 29, 2002DIA | US$ 1.5 M | SMA |
| Exploraciones Sector PurenMetallic mining · Minera Puren | Compañía Minera Mantos de Oro | AtacamaCopiapó | May 8, 2002DIA · RCA 46/2002 | US$ 500 k | SMA |
| Explotación Molienda y Transporte de Silice en Yacimiento NancyNon-metallic mining · Explotación Molienda y Transporte de Silice en Yacimiento Nancy | — | AntofagastaSierra Gorda | Apr 18, 2002DIA | US$ 360 k | SMA |
| Modificación Proyecto Cátodos Segunda EtapaMetallic mining · Michilla | Minera HMC S.A. | AntofagastaMejillones | Apr 4, 2002DIA · RCA 78/2002 | US$ 51.4 M | SMA |
| Explotación de Magnetita Contenida en Depósitos AluvialesMetallic mining · Concentrados de Magnetita - Chile Exploration And Mining S.A. | Chile Exploration And Mining S.A. | CoquimboLa Higuera | Mar 26, 2002RCA 68/2002 | US$ 360 k | SMA |
| Botadero de Lastre 2Metallic mining · El Abra | SCM El Abra | AntofagastaCalama | Mar 26, 2002DIA · RCA 66/2002 | US$ 5.3 M | SMA |
| Aumento de la Capacidad de Producción de Sulfuros de Baja LeyMetallic mining · Codelco Chuquicamata | Codelco | AntofagastaCalama | Mar 12, 2002DIA · RCA 55/2002 | US$ 4 M | SMA |
| Optimización de la Capacidad de la Concentradora A-0 a Traves de la Reutilización de Sus Equipos ExistentesMetallic mining · Codelco Chuquicamata | Codelco | AntofagastaCalama | Mar 6, 2002DIA · RCA 46/2002 | US$ 9.1 M | SMA |
| Optimización Concentradora A-2Metallic mining · Codelco Chuquicamata | Codelco | AntofagastaCalama | Mar 6, 2002DIA · RCA 47/2002 | US$ 690 k | SMA |
| Tranque de Relaves Poniente Planta El Maiten IllapelMetallurgy · Tranque de Relaves Poniente Planta El Maiten Illapel | Sociedad Aguirre Moyano | CoquimboIllapel | Feb 22, 2002DIA | — | SMA |
| Mina PorfinNon-metallic mining · Mina Porfin - San José de Maipo | Yesotec S.A. | Metropolitana de SantiagoSan José de Maipo | Feb 18, 2002EIA | US$ 15 M | SMA |
| Expansión División AndinaMetallic mining · Codelco - División Andina | Codelco | ValparaísoTiltil, San Felipe, San Esteban, Rinconada, Los Andes, Colina, Calle Larga | Feb 15, 2002EIA · RCA 29/2002 | US$ 650 M | SMA |
| Proyecto Desarrollo Fundición CaletonesMetallic mining · Mina El Teniente y Fundición Caletones | Codelco | Libertador General Bernardo O'HigginsMachalí | Feb 7, 2002DIA · RCA 16/2002 | US$ 150 M | SMA |
| Explotación Minera a Cielo Abierto de Mantoruso en Faena MantoverdeMetallic mining · Minera Metálicamanto Verde de Mantos Copper | Mantoverde S.A. | AtacamaDiego de Almagro | Feb 6, 2002DIA · RCA 18/2002 | — | SMA |
| Proyecto Minero AldebaranMetallic mining · Barrick -Cerro Casale | Sociedad Norte Abierto SpA | AtacamaTierra Amarilla, Copiapó | Jan 31, 2002EIA · RCA 14/2002 | US$ 1,430 M | SMA |
| Cantera Zona 71 ExteriorNon-metallic mining · Mina El Navio | Melon S.A. | ValparaísoNogales | Jan 31, 2002DIA · RCA 14/2002 | US$ 3 M | SMA |
| Proyecto Tranque de Relaves Sector La Higuera-Planta TalcunaMetallic mining · Minera Rendic | Cía. Mra. San Gerónimo | CoquimboVicuña | Jan 21, 2002DIA · RCA 11/2002 | — | SMA |
| Extensión Planta de YodoNon-metallic mining · Extensión Planta de Yodo DSM Minera - Pozo Almonte | DSM Minera S.C.M. | TarapacáPozo Almonte | Jan 21, 2002DIA · RCA 17/2002 | US$ 4 M | SMA |
| Proyecto CaquicitoMetallic mining · Proyecto Caquicito | Anglo American Sur | ValparaísoNogales | Jan 7, 2002EIA · RCA 3/2002 | US$ 4 M | SMA |
| Proyecto CaquicitoMetallic mining · Mina El Soldado | Anglo American Sur | ValparaísoNogales | Jan 7, 2002EIA · RCA 3/2002 | US$ 4 M | SMA |
| Optimización Faena Minera Lomas Bayas Pozo CMG-1Metallic mining · Lomas Bayas | Compañía Minera Lomas Bayas | AntofagastaCalama | Dec 31, 2001DIA · RCA 298/2001 | US$ 50 k | SMA |
| Saneamiento Ambiental de Cerro JaronMetallic mining · Minera Escondida | Minera Escondida | Antofagasta | 2001RCA 4/2001 | — | SMA |
| Modificación Línea de Transmisión Subestación Polpaico - Subestación Sag Entre Los Vertices V33 y V43Metallic mining · Codelco - División Andina | Codelco | Valparaíso | 2001RCA 8/2001 | — | SMA |
| Instalación de Almacenamiento Prolongado de Residuos PeligrososMetallic mining · Codelco Chuquicamata | Codelco | Antofagasta | 2001RCA 149/2001 | — | SMA |
| Ampliación de Planta Carbonato de Litio a 32.000 Ton/AñoNon-metallic mining · SQM Salar Atacama | NovaAndino Litio (ex SQM Salar) | Antofagasta | 2001RCA 100/2001 | — | SMA |
| Instalación de Combustibles y Lubricación en Mina EscondidaMetallic mining · Minera Escondida | Minera Escondida | Antofagasta | 2001RCA 85/2001 | — | SMA |
| Actividad de Tranporte de Polvo de Zinc Gas Licuado de Petroleo Litargirio y Nitrato de PlomoMetallic mining · El Peñón | — | Antofagasta | 2001RCA 113/2001 | — | SMA |
| AcueductoMetallic mining · Mantos de la Luna | Cía. Minera Mantos de la Luna S.A. | Antofagasta | 2001RCA 164/2001 | — | SMA |
| Transporte de Sulfato de Cobre CristalizadoMining | — | Antofagasta | 2001RCA 131/2001 | — | SMA |
| Limpieza Aguas Mina AndinaMetallic mining · Codelco - División Andina | Codelco | Valparaíso | 2001RCA 941/2001 | — | SMA |
| AciductoMetallic mining · Radomiro Tomic | Codelco | Antofagasta | 2001RCA 179/2001 | — | SMA |
| Manejo de Residuos y Subproductos de Planta Prototipo BiocopMetallic mining · Codelco Chuquicamata | Codelco | Antofagasta | 2001RCA 235/2001 | — | SMA |
| Terminal para la Descarga de Ácido Sulfúrico Desde Camiones - Estanque en las Instalaciones de SCM El AbraMetallic mining · El Abra | SCM El Abra | Antofagasta | 2001RCA 223/2001 | — | SMA |
| Traslado Planta de Tratamiento de Agua PotableMetallic mining · Codelco Chuquicamata | Codelco | Antofagasta | 2001RCA 236/2001 | — | SMA |
| Instalación de Estanques de Almacenamiento de Apoyo al Taller de Mantención MinaMetallic mining · Minera Escondida | Minera Escondida | Antofagasta | 2001RCA 261/2001 | — | SMA |
| Construcción y Operación Subestación Eléctrica Minero 220/110 KV.Metallic mining · Mina El Teniente y Fundición Caletones | Codelco | Libertador General Bernardo O'Higgins | 2001RCA 105/2001 | — | SMA |
| Traslado Planta de Servicios de TronaduraMetallic mining · Minera Escondida | Minera Escondida | Antofagasta | 2001RCA 251/2001 | — | SMA |
Source: public registers of Chile's environmental regulator (SMA). Investment is what the holder declared when the project was assessed, in dollars of that year; it is not actual spend. Approvals after 2016 come from the RCA register and carry no investment or exact day. Projects of natural persons are shown without a name.